Indian Railways Sets Record: Subway Built In Just 4.5 Hours Using THIS Method

Advertisement
1/6
Record Construction Time
Record Construction Time

Indian Railways constructed a limited-height subway in just 4.5 hours between Pendurthi and Kottavalasa in Andhra Pradesh, creating a record.

Share
2/6

"The limited height subway work, which was done a few months back consists of 20 segments of 1.5 m width while the size of the box is 4.65 m X 3.65 m. These 20 segments had been launched in four and a half hours," said a railway official posted at the East Coast Railway (ECR) in Visakhapatnam, India Today reported.

Share
3/6
Massive Equipment Used
Massive Equipment Used

The project utilized 16 heavy-duty excavators, 3 cranes, 5 tippers, 4 hydra machines, heavyweight jacks, 1,000 sandbags, and a 300-member workforce.

Share
4/6
Execution Process
Execution Process

Once the block started, tracks were removed, earthwork began from both ends, and prefabricated boxes and base slabs were placed with the help of cranes.

Share
5/6
Time Breakdown
Time Breakdown

Earthwork and surface preparation took 1 hour, box placement and track linking took 1.5 hours, totaling the construction block to just 4.5 hours.

Share
6/6
Operational Impact
Operational Impact

With the subway now operational, the manned level crossing has been closed, significantly reducing the risk of accidents. ( Representative Images: Freepik)

Share